Question

Problem 11-115 Jaster Corporation s management…

Jaster Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order:

Compute the throughput time.(Round your answer to 2 decimal places.)

Compute the manufacturing cycle efficiency (MCE). (Do not round intermediate calculations. Round your answer to nearest whole percentage. Omit the “%” sign in your response.)

What percentage of the production time is spent in non-value-added activities? (Do not round intermediate calculations. Round your answer to nearest whole percentage. Omit the “%” sign in your response.)

Compute the delivery cycle time. (Round your answer to 1 decimal place.)

 

Jaster Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order:

 



Source link